Let’s paddle the
AssawomanCanal or what’s left of it.
Update Nov 15 postponed
till Nov 22
Want a chance to practice some cold water paddling in a protected
area? Join us Saturday Nov 22nd.
Several of us are
looking at meeting at the
KentBridge launch site Saturday November
22ndh,
that’s next Saturday morning, probably around 10:30. The canal
is a protected area that is slowly being dredged. It might be
interesting to see how far they have come with their project. It
doesn’t look like much is being done.
It is a sheltered area usually free of
any strong winds, the water is shallow, and generally warmer than the
adjoining bays so even “No Big Water” can get her boat out for one last
ride. We can paddle in to Bethany Beach if the tides are low, or even
out into the Salt Pond. This can really be a rain or shine paddle.
Several years ago in the middle of a nor’easter we paddled it and could
hardly tell it was thrashing the beach just a couple miles away.
And there are plenty of places to grab
a bite afterward including Dogfish
Head and The Dewey
Beach Club. Ocean View has small pubic bathrooms at the park
close by that could be used for changing after the paddle.
Directions are on the put-in page,
scroll down about halfway to The Assawoman Canal at the Kent Ave Bridge.
Update May 7th 2008,
The canal is still very paddleable, if that's a word. Launch from
the Kent Ave put-in. There is
also a Marina where you can launch for a small fee at the end of Elliot
Ave in Ocean View. This dredging project will cost the State a fair
bit of money, there is no science showing that it will be of any real
value in helping to flush the Inland Bays, and there is at least one
engineering firm that thinks the increased flows will add to the flooding
of downtown Bethany Beach via the
Loop Canal at extreme high tides. But the boaters of South
Bethany will be able to go out the Indian River Bay to fish, and that
should increase their property values which is of course important.
They can't seem to find the money to replace the flat launch spot at Haven
Road that was very useful for adaptive paddle instruction, but they have
money to dredge a canal that will fill right back in if they don't control
boat wakes. Such as it is.
Click on the images below for a
larger version
Looking south from the Central Ave Bridge.
The trees have been heavily thinned out on the east side.
Looking north from the Central Ave Bridge.
The trees have been removed on the west side.
Looking north from the Kent Ave Bridge, the
hydraulic dredging pipe is lying against the west (left) bank.
Looking south that same pipe
is on the right. It is currently out into the canal but still very manageable.
What is lost is the ability to slip through a small gut and into a pond to
the west of the canal. That pond should still be accessible further
on down the canal towards the Little Assawoman Bay.
47-years have elapsed since the canal was last dredged (draglined), and then
only to a channel width of 20-feet. The original 1957 specifications called
for complete clearing and leveling of all trees along both banks of the
canal’s entire 200-foot right-of-way. However, due to 1958 state funding
constraints, the trees were not cleared as planned.
According to an April 11, 1957, article in the DELMARVA
NEWS, one of the main expected benefits from dredging the canal was "the
contention that it would increase the resort business of Sussex County, and
also accrue greater monies to the State through improved values and sale of
real estate along the myriad inland waters that would be opened up for
continuous boating all the way from Lewes to Fenwick Island." DNREC has
denied that this is a purpose of the currently proposed dredging.
The Assawoman Canal dredging project was originated in 1886
as part of a waterway from Chincoteague Bay, VA, to Delaware Bay, near Lewes,
DE, for the purpose of transporting farm produce to markets, prior to the
advent of automobiles and paved roads on the Delmarva peninsula. The River and
Harbor Act of March 1905 repealed the partially completed project.
The federal intra-coastal waterway project was deauthorized
by U.S. Public Law in December 1981 as a result of opposition by
53-organizations, including the: American Littoral Society, Audubon Naturalist
Society, Canoe Cruisers Association, Delaware Friends of Coastal Zone,
Delaware Nature Education Center, Delaware Wild Lands, Environmental Defense
Fund, Environmental Policy Center, Friends of the Earth, Izaak Walton League
of America, National Audubon Society, National Wildlife Refuge Association,
National Wildlife Federation, Nature Conservancy, and Sierra Club.
Since 1984 Delaware politicians and DNREC have been working
to have the canal redredged.
Estimated Motorized Boat Sizes After Dredging:
DNREC expects the dredged canal to be used primarily by
small Boston Whalers, pontoon boats and other similar vessels with an average
length of 13 to 20 feet and an average width of 5 to 8 feet.
When passing in opposite directions these vessels will have
approximately 6-feet of clearance from the edges of the channel and 6-feet of
clearance in the middle of the channel. DNREC admits that taking tidal current
and wind conditions into consideration, these clearances do "not leave a
lot of room for error."
Estimated Motorized Boat Usage After Dredging:
DNREC estimates that after dredging the average number of
motorized boat trips through the canal will increase from 2 per day to
approximately 74 per day, or about 518 per week (14,504 annually) during the
28-week boating season, excluding increased traffic from the Harbour View
Marina.
Safety of Waterway After Dredging is Questionable:
DNREC claims the dredged canal will "ensure a safe
navigable channel for the boating public." The Sierra Club believes the
anticipated high volume of motorized boat traffic in this extremely narrow,
35-foot wide, waterway will create an inherently unsafe condition, especially
with powered and non-powered vessels sharing the canal.
Completed July 8, 1910, the Loop Canal marked the end of a long journey for
vacationers traveling to Bethany Beach in the town’s early days. Arriving in
Rehoboth by railroad, travelers would continue their voyage by boat, crossing
Rehoboth and Indian River Bays to the U. S. Government (Assawoman) Canal. For a
time, the final portion of the trip was completed in a two-horse drawn bus
through the deep sand to the town. In an effort to improve travel conditions, a
shallow waterway was dredged from the Assawoman Canal to this location.
Approximately 1½ miles in length, it was constructed by the Bethany Beach
Improvement Company, an organization of developers and property owners. With the
opening of the canal, travelers could complete the final leg of the journey by
boarding a single boat in Rehoboth. Since the shallow-draft motorboat Allie
May could not back up, a loop was formed here at the First Street dock to
allow the boat to turn around for the return trip.
The state’s Department of Natural Resources and Environmental Control (DNREC)
may start work on the Assawoman Canal dredging project as early as mid-January,
according to DNREC’s Chuck Williams (Soil and Water Conservation).
The Sierra Club has repeatedly criticized DNREC for: (1) a lack of scientific
rigor in checking for environmental impacts, and (2) an incomplete cost-benefit
analysis. However, Delaware’s Court of Chancery ruled in favor of the state last
week, on a matter appending the Sierra Club’s most recent appeal.
“As far as I know, we have clearance to move forward,” Williams said.
“Chancery denied the injunction — of course, it remains to be seen if the Sierra
Club is going to appeal to the next higher court.”
Williams said the dredging season — “in-water” work, at any rate — is
confined September through December, for environmental reasons. Therefore, any
work until next fall will strictly consist of preparations at the spoils sites
(where the state will pile the dredged materials) and along the banks (where
DNREC will clear away vegetation to make way for mechanical dredging from the
bank).
DNREC and the Army Corps of Engineers would be working hand-in-fist on that
portion of the project, Williams said, to keep any clearing to a minimum.
“We’ll be moving forward with that by next month, if at all possible,” he
pointed out. Williams said he was in the process of assembling a construction
plan.
DNREC had waited to see how the Chancery would rule before moving forward,
and Williams said that had been a voluntary inaction. He couldn’t say whether
the department would once again hold back in the event that the Sierra Club
petitioned to a higher court.
“Whatever our legal counsel advises,” he said.
Despite some indication that the dredging project may actually become a
reality, local Rep. Gerald Hocker (38th District) suggested things still weren’t
moving as quickly as they could be. He would have preferred to see some actual
dredging this fall, or at least a start on the peripheral work.
Hocker noted efforts to get the project moving, stretching back 18 years,
through the administrations of four separate governors. And he said the state
had come to terms with the Sierra Club on many counts.
Originally intended to take the Assawoman Canal down to a depth of 5 or 6
feet, the project had been modified to a more modest dredge to 3 feet, mean low
tide, he pointed out.
“If there’s something major the Sierra Club wants, I think we’re all willing
to sit down and compromise — and we’ve done that,” Hocker said. “But we’ve been
trying to compromise for 18 years, and I think you can only compromise so much.”
It has been three weeks since the Sussex Conservation District
broke ground on the Assawoman Canal dredging, on Oct. 3. DNREC
project manager Chuck Williams said this week, “We’ve been making
good progress with the mechanical dredging.”
Williams said that though there were hopes to get ahead with the
hydraulic dredging of the south portion of the Canal, there were
some minor complications. “We hope to hit it hard next year,” he
said of the south end.
The six members from the Sussex Conservation District have moved
along the canal and are currently behind the Bethany Beach Surf Shop
on Route 26, continuing the mechanical dredging process.
The mechanical dredging involves using a long-reach excavator to
remove the soil, creating new dimensions of 35 feet of width and 3
feet of depth for the canal. The project is expected to remove about
34,000 cubic yards of material by its completion.
The soil removed is currently being taken to Fresh Pond State
Park, the first designated spoils site. Sierra Club member Steve
Callahan is opposed to this spoil location. “The state is destroying
this area simply because it is closest to the canal,” he said. “They
want it dredged so badly they don’t care about the side-effects.”
Callahan was concerned with the young forest of loblolly pines
that was bulldozed for the site and the potential threat to the
emergent wetlands and fertile soil already on the property. “A
larger area then necessary is being decimated,” he said.
Williams responded to some concerns about the maintenance of the
spoils site. He said the Fresh Pond State Park is just a primary
disposal location. He said once the soil has been taken to the site,
it will be analyzed more extensively to see if it is suitable for
other purposes.
Williams said there are hopes the soil can be used to aid the
diamondback terrapin nesting area north of the Indian River Inlet.
He also stated there is potential for the sandy sediment to aid in
beach replenishment if deemed suitable. Of the destroyed trees,
William said, “Loblollies aren’t endangered. There are intentions to
restore and re-vegetate that area.”
Meanwhile, the Sierra Club gave their final briefing to the
Delaware Supreme Court for their legal appeal against DNREC and the
dredging process last Friday, Oct. 20. Sierra Club attorney Kenneth
Kristl said the main aspect of the appeal is questioning the purpose
of Section 81 of last year’s state bond bill.
That bond bill approved the funding for the dredging project
while the Sierra Club was still in the appeals process to stop it,
bypassing calls for more extensive studies of the project.
The Sierra Club appealed the 2004 permit allowing the dredging in
a 2005 hearing before the Environmental Appeals Board. Before the
board issued its late-July opinion that ordered a cost-benefit
analysis for dredging, however, the General Assembly in June 2005
approved the project in Section 81 of the bond bill.
“It is the express finding of the General Assembly that the
benefits of dredging and maintaining the Assawoman Canal exceed the
costs of such project and the Secretary of Natural Resources and
Environmental Control is hereby directed to initiate all necessary
actions to dredge the Canal,” Section 81 of that bond bill reads.
Kristl said the biggest question the Sierra Club has in their
appeal the Delaware Supreme Court is, “What is the effect of Section
81?”
Kristil said that if their arguments are successful, the dredging
project, which is forecasted to take about three years to complete,
should be halted. “DNREC would have to go back and get the proper
permits in order to continue dredging,” said Kristil.
The Dredge
The Assawoman Canal dredging project involves both mechanical and
hydraulic dredging methods from the northern end of the waterway at
its confluence with White Creek, to the southern end of the waterway
at Little Assawoman Bay. The channel will be dredged to a width of
35 feet and a depth of 3 feet below mean low water (MLW). An
estimated 34,000 cubic yards of material will be removed from the
canal as part of the project. Material will be pumped via pipeline
to a second upland disposal facility located on property owned by
the Division of Fish and Wildlife.
About a dozen kayakers and a couple canoeists, Sierra Club
members and guests, toured the Assawoman Canal on Sept. 25, for what
may be one of the last trips down the canopied waterway, as it
exists today. Several days earlier, the Department of Natural
Resources and Environmental Control (DNREC) had marked trees for
clearing, in preparation for the long-anticipated dredging project
that will open the canal to a larger boating public — but, from some
viewpoints, diminish its attractiveness to paddlers. Coastal
Point • SAM HARVEY: Bill Ahlers and Ron Zink take the tour.
As it stands, there are several shoals along the canal, the worst
low spots being at the intersection of the Loop and Assawoman
canals, and under bridges at Route 26 and Kent Avenue. Ironically,
dredge supporters are at least in part seeking to address silting in
that occurred when the state raised those bridges — specifically to
accommodate the passage of medium-sized craft — in the mid- to
late-1980s.
The bridges were due for replacement anyway, but as Sen. George
Howard Bunting (20th District) recently noted, there’d been much
discussion, work and compromise en route settlement on those
increased clearances.
In preparation for completing the job, DNREC issued initiated the
permitting process shortly thereafter — and the project entered its
nearly 20-year stretch in the bureaucratic tar pits. The Assawoman
Canal has probably never been more shallow, since the time the
area’s early settlers hand-excavated it, near the turn of the 20th
Century.
It was partially drag-lined in the late 1950s, but the state
turned away from efforts to continue recreational improvements along
a proposed inter-coastal waterway in the years that followed.
There are at least a few kayakers and canoeists around who would
have preferred the state maintain that stance — Callanen said about
half the people paddling out on Sept. 25 were from the area.
He described their kayak outing as the perfect autumn day — sun
shining, temperature not too hot, not too cold, the quiet stretches
along the canal, the blue herons and kingfishers along the banks,
the overarching canopy.
Even setting out just past low tide, he said they never had to
get out and push. Heading north toward White Creek, they came upon a
pontoon boat at the intersection of Loop and Assawoman — while the
captain had bumped onto the shoals, they advised him to wait a few
minutes, and he’d be clear, Callanen recounted. True to their
prediction, the larger boat overtook them about 20 minutes later, he
said.
“There’s no question, it doesn’t meet their drawing board
requirements (20 feet wide, 3 feet deep), but if they wanted to make
it passable for small motorboats, all they’d have to do is clean out
these three areas (Loop Canal, Route 26, Kent Avenue),” he noted.
“But they don’t want to do that.”
Callanen has been fighting this dredging project, with some
vigor, for several years now. But completely aside his preferences
for the canal as it has transformed itself, into a seemingly
natural, virtually un-traveled waterway, what he’s been protesting
all along is what he considers a lack of proper procedure. “If the
canal’s going to be dredged, so be it,” Callanen proclaimed. “But,
at least, I’d like to see everybody being honest and up-front about
the permitting process.”
On the opposite side of the aisle, Assawoman Canal dredging
supporters (while criticizing DNREC for delays caused by paperwork
mix-ups) have defended the rigor of the studies justifying the
project. And given the nearly 20-year timeline, it appears no one
actually succeeded in greasing a skid.
Callenen still questioned the process, however, suggesting DNREC
should have performed a more rigorous environmental impact
assessment at the outset. And as the state’s own Environmental
Appeals Board ruled (overruled by the General Assembly and the
Governor), DNREC should have recalculated its cost/benefit analysis.
However, he could offer no advice, regarding how best to
encourage change in state practice and procedure toward what he’d
consider greater fairness and objectivity in project evaluation.
“I’d just like to shed some light on the process,” Callanen
concluded. “It probably won’t do any good. But years from now, when
there are boats roaring up and down the canal and the banks are
eroding, I will be able to say, ‘At least I tried.’”
The Mid-Atlantic Environmental Law Center (MAELC) had its day in
court on Feb. 22, completing the latest chapter in Assawoman Canal
re-dredging saga.
Attorney Ken Kristl, representing the Sierra Club, echoed the
concerns voiced in last year’s appeal. Coastal
Point • SUBMITTED: Hocker
Much of the argument references a document titled the “Assawoman
Canal Dredging Project Assessment Report.”
“The Sierra Club believes there are significant problems with
that report,” Kristl said. “There’s a lack of important information
– they just haven’t answered the fundamental questions.”
According to Kristl, the report doesn’t properly address
environmental impacts like erosion along the shoreline or potential
damage to a biologically productive area.
“The canal is an essential fish habitat,” Kristl stated.
Others have disputed the claim that the re-dredging will hurt
marine life, among them Rep. Gerald Hocker (38th district).
He said a re-dredging in 1958 had improved water quality, and
increased marine life returned to the canal following the project.
“I just wish common sense would play a little part in this,” he
said. “How can fish and crabs live in an area where there’s no
water?
“The last thing we want in Sussex County is more dead-end
canals,” Hocker stated. “We maintain our tax ditches better than we
do the Assawoman Canal.”
The MAELC has raised concerns regarding impacts at the spoils
sites. The state estimated they would need to dispose of 34,000
cubic yards of material, split between an old spoils site near South
Bethany, at the south end, and the Fresh Pond State Park, near the
north end.
There was mention of possible disposal on the beach, near
Bethany, as well.
The cost-benefit analysis also remains a bone of contention —
although DNREC claimed it withdrew its own permit in April 2004
because of a public record anomaly regarding environmental issues,
the Sierra Club claimed it was because the department hadn’t
provided an economic study until after the close of the public
comment period.
The Army Corps of Engineers did complete a cost/benefit analysis
as part of approving the project, but the Sierra Club questioned its
rigor.
According to Hocker, DNREC bought the canal from the Army Corps
specifically for recreational use, but as it continued to fill in,
it was becoming less and less well-suited for recreation.
• Circa 1900 — the 3.9- mile Assawoman Canal is hand-dug by the
area’s early settlers.
• 1957 — Gov. Caleb Boggs signs an appropriation bill for
re-dredging, to a depth of four feet.
• 1958 — Atkins Brothers start drag-lining, and the project is 60-65
percent complete by February (followed by a gap in the record).
• 1976 — midway through a project to run sewer mains to South
Bethany, a nor’easter washes cofferdams into the canal.
• 1990 — Parks and Recreation acquires the canal, and lands along
the bank, from the Army Corps of Engineers. The state issues a
permit for re-dredging.
• 1995 — the Sierra Club points out that the permit has expired, and
asks the state to reissue.
• 2002 — the state reissues the permit. The Sierra Club appeals the
decision.
• April 2004 — the Sierra Club has its day in court, but the state
withdraws its own permit before answering that testimony, citing a
clerical omission.
• August 2004 — at the urging of local legislators, the permit is
reissued on a fast track. The Sierra Club once again appeals the
decision.
• Feb. 22, 2005 — the Sierra Club has returns to court, and awaits
answering testimony from DNREC — slated for March 22.
If approved, according to the DNREC press release, the canal will
be widened to 35 feet and dredged to 3 feet below the mean low tide
mark.
The state will stabilize 220 feet of the western bank with a
modified form of concrete riprap.
Permit conditions include establishment and enforcement of a no-wake
zone and a prohibition on marina development along the canal.
The state will also have to monitor the canal for dissolved
oxygen and bacteria levels, to evaluate how the dredging impacts
water quality.